Title |
---|
Environmental and Social Management and Monitoring Plan Construction Phase Entire Construction Work, March 2014 |
Biomass Removal Plan, July 2015 |
Biodiversity Offset Framework, March 2015 |
53. SS-ESMMP for Land Leveling for Project Affected People of Hatsaiykham at Houay Soup Resettlement Area, February 2016 |
52. SS-ESMMP of Enhancement Works on Road Conditions at Houay Soup Resettlement Area |
51. SS-ESMMP-CP for Workers Camp, October 2015 |
50. SS-ESMMP for PC Bridge Construction, November 2015 |
49. SS-ESMMP of UXO Clearing Work, April 2015 |
48. SS-ESMMP for Foundation,Erection and Stringing Work, May 2015 |
47. SS-ESMMP for Clearing Right of Way, April 2015 |
46. SS-ESMMP of Site office stockyard and camp, April 2015 |
45. SS-ESMMP for Worker Camps, November 2014 |
44. SS-ESMMP for Contractor’s Camp, May 2014 |
43. SS-ESMMP for Building of Owner’s Base Camp, December 2014 |
42. SS-ESMMP for F-I &O of Aggregate Crushing Plant, January 2015 |
41. SS-ESMMP for Clearing Earthworks&Operation of Waste Disposal |
40. SS-ESMMP for Construction of Quarry Site, November 2014 |
39. SS-ESMMP for Power Supply Systems Installation Works, July 2014 |
38. SS-ESMMP for IPD of Tower Crane at MD, December 2015 |
37. SS-ESMMP for Construction Main Power House, December 2016 |
36. SS-ESMMP for Grouting Work of Secondary Upstream Cofferdam, January 2016 |
35. SS-ESMMP of Limb Grouting Tunnel of Main Dam, June 2015 |
34. SS-ESMMP of River Diversion Tunnel Works, October 2014 |
32.SS-ESMMP for Encased Concrete&Retaining Wall at Outlet Tunnel Entrance |
31. SS-ESMMP of Installation for RCC Belt Conveyor System, June 2015 |
29. SS-ESMMP for RD Structure Works at Inlet and Outlet, November 2014 |
28. SS-ESMMP for CVC Plant, August 2014 |
27. SS-ESMMP for Dyke Construction at Regulation Dam, November 2015 |
26. SS-ESMMP for Excavation&Construction Work of Secondary Upstream Cofferdam, December 2015 |
25. SS-ESMMP for Construction of Primary U&P Cofferdam, October 2015 |
24. SS-ESMMP for Clearing&Earthwork of Waste Disposal Area, December 2014 |
23. SS-ESMMP for Re-regulation Power Station, February 2015 |
22. SS-ESMMP for Slope Protection&Slope Drainage of Main Dam, Apr 2015 |
21. SS-ESMMP for Construction of Main Dam Excavation Works, Sep 2014 |
20. SS-ESMMP for RD Structure Works at Inlet & outlet, Nov 2014 |
19. SS-ESMMP for Aggregate Plant Earth Works, Sep 2014 |
18. SS-ESMMP for Plant Yard, May 2014 |
17. SS-ESMMP for Temporary Bridge, Feb 2014 |
16. SS-ESMMP for Disposal Area at Right Bank, Oct 2014 |
15. SS-ESMMP for Quarry of Road A, March 2014 |
14. SS-ESMMP for Road T13, May 2015 |
13. SS-ESMMP for Road T12, Dec 2013 |
12. SS-ESMMP for Road T11, Nov 2014 |
11. SS-ESMMP for Road T10, Nov 2014 |
10. SS-ESMMP for Road T9, May 2015 |
9. SS-ESMMP for Road T8, Dec 2014 |
8. SS-ESMMP for Road T7, Jul 2014 |
7. SS-ESMMP for Road T5, Dec 2013 |
6. SS-ESMMP for Road T4, May 2015 |
5. SS-ESMMP for Road T3, Dec 2014 |
4. SS-ESMMP for Road T1 and T2, May 2015 |
3. SS-ESMMP for Road P2, May 2015 |
2. SS-ESMMP for Road P1, May 2015 |
1. SS-ESMMP for Road A, Apr 2015 |
30. SS-ESMMP for Foundation&Installation of RCC Plant, Feb 2015 |
54. SS-ESMMP for BIOMASS REMOVAL IMPLEMENTATION, 04 April 2016 |
55. SS-ESMMP for Electric installation on HSRA, 04 April 2016 |
SS-ESMMP-CP for Installation Work of Spiral Case and Stay Ring for Main Power Station |
SS-ESMMP-CP for HM's Sub-contractor Labor camp No.2 |
SS-ESMMP-CP for Draft tube liner Installation at Main Powerhouse |
SS-ESMMP-CP for Installation Work of 630kVA Transformer for Re-regulation power station |
SS-ESMMP-CP for Installation Work of Embedded Parts of 230 kV Substation for Main Power Station |
SS-ESMMP-CP for Fabrication Work of Concrete Weight |
SS-ESMMP-CP for Zhefu warehouse |
SS-ESMMP-CP for installation Work of 80 ton Electrical Overhead Traveling Crane for RPS |
SS-ESMMP-CP for CSG & SR Installation (Installation Work of Spiral Case and Stay Ring for Main Power Station) |
SS-ESMMP-CP for Installation Steel Structure for 115kV, TL |
SS-ESMMP-CP for Installation of Inlet Valve and Servomotor for Main Power Station |
SS-ESMMP-CP for Sub-Contractor Camp |
SS-ESMMP-CP for 38 ha paddy field development on Houay Soup Resettlement Area |
SS-ESMMP for Construction of tractor road on Houay Soup Resettlement Area |
SS-ESMMP-CP for Biomass Clearing |
SS-ESMMP for 48 ha Paddy field development project for 2LR people |
SS-ESMMP for Construction of Intake mouth canal at Houay Soup Resettlement Area |
SS-ESMMP for construction of Intake, Inlet and outlet Canals at Houay Soup Resettlement Area |
SS-ESMMP for Land levelling (Cutting & Filling) for 90 house plots at HSRA |
SS-ESMMP for 231ha UXO Clearance for Houay Soup Resettlement Area |
SS-ESMMP for Construction of Outlet canal and 4 Sub canals |
SS-ESMMP for (7Units) House Construction |
SS-EMP for Village Office and Hall Construction at HSRA |
SS-ESMMP for Road Construction to Landfill 1.2km |
SS-ESMMP for Irrigation Dam Reservoir Land Clearance |
SS-ESMMP for 28 Plots Land Levelling |
SS-ESMMP for House Construction Lot No 3 at Houay Soup Resettlement Area |
SS-ESMMP for Resource center construction and Pilot plan improvement at Houay Soup Resettlement Area |
SS-ESMMP for Construction of 84 fish ponds at Houay Soup Resettlement Area |
SS-ESMMP for temporary Accommodations for 44 households from 2LR |
SS-ESMMP for Installation 0.4kV distribution line for 7 houses |
SS-ESMMP for Domestic water supply system construction |
SS-ESMMP for Construction of Primary School 3 Units at 2UR |
SS-ESMMP for filling residential lands and lift up house (between El320m-321m) at 2UR |
SS-ESMMP for Owner Site Office and Village (OSOV) rev A4 |
SS-ESMMP for Contractor's Camp |
SS-ESMMP for Encased Concrete & Retaining Wall at Outlet |
|
SS-ESMMP for Casting Replacement Concrete of MD |
SS-ESMMP for Adit Closure at Right Bank of Main Dam |
SS-ESMMP for Closing Procedure of Dyke Borrow Pit No.7 (A1) |
SS-ESMMP for Biomass Clearance Works of Re-regulation pond of Re-regulation Power Station |
SS-ESMMP for EMO Water Quality Laboratory Construction |
SS-ESMMP-CP for Soccer field construction |
Watershed and Biodiversity Management |
ESMMP-CP for Project Component Sub-Plans, May 2017 |
ESMMP-CP for Thematic Sub-Plans, May 2017 |
ESMMP-CP for Procedures, May 2017 |
ESMMP-CP for General Matters, May 2017 |